A project manager in a seller organization discovered that certain deliverables had been handed over to the buyer without undergoing proper testing. Recalling the deliverables will result in a cost overrun to the project. What should the project manager do in such a case? A. Recall the deliverables even though there will be a cost
PMP Exam Set G – Q70
Jane is managing a project in a Functional organization. In this organization, she can expect to find that: A. She wields considerable authority and can make independent decisions related to the project.B. Management systems are designed to support projects and project management is easy.C. Management systems are not designed to support project needs efficiently, and
PMP Exam Set G – Q69
A measure taken to bring future results in line with the project plan BEST describes? A. Change requestB. Preventive actionC. Corrective actionD. Defect repair Show Answer C. Corrective action
PMP Exam Set G – Q68
A first-time project manager was assigned to a project that had a duration of 3 months. In order to gain a head start in the project, she took an older, completed project and incorporated all the tools, techniques and checklists from that project in their entirety into the current one. The older project had been
PMP Exam Set G – Q67
Your project team has recently identified a risk in the software development project and decided not to change the project management plan to deal with the risk. The risk response strategy your team used in this scenario is an example of: A. MitigateB. TransferC. AvoidD. Acceptance Show Answer D. Acceptance
PMP Exam Set G – Q66
Which of the following should you NOT use as an input into creating the WBS structure? A. Bill of Material (BOM)B. Project scope statementC. Organizational process assetsD. Requirements documentation Show Answer A. Bill of Material (BOM)
PMP Exam Set G – Q65
You have just completed the first phase of a multi-phase project. You have performed the earned value measurements and found out that the current CPI is 0.79, the current SPI is 0.98. Your next phase plan should focus first on which element of the project? A. QualityB. ResourcesC. ScheduleD. Cost Show Answer D. Cost
PMP Exam Set G – Q64
A detailed milestone list is created as an output of what process? A. Sequence ActivitiesB. Define ActivitiesC. Develop Project CharterD. Develop Schedule Show Answer B. Define Activities
PMP Exam Set G – Q63
Which of the following is not a general management technique used to generate different approaches to execute and perform the project work? A. Lateral thinkingB. Analysis of alternativesC. Map OutD. Brainstorming Show Answer C. Map Out
PMP Exam Set G – Q62
You have been assigned as project manager of a software development project. One of the requirements is to use a remote team and you find that that the remote team has limited technical communications capabilities. This is an example of: A. An assumptionB. A hindranceC. A show-stopperD. A constraint Show Answer D. A constraint