PMP Exam Set A – Q31

Bottom-up Cost estimating is typically motivated by the size and complexity of:

A. The project management software
B. The statistical relationship between historical data and other variables
C. The project budget.
D. The individual schedule activity or work package

D. The individual schedule activity or work package