PMP Exam Set A – Q38

Which option is NOT representative of the inputs, tools and techniques, and outputs of the Direct and Manage Project Work process?

A. PMIS, Project Management Plan, and Deliverables
B. Deliverables, Approved Change Requests, and Project Management Information System
C. Approved Change Requests, Validated Changes, and PMIS
D. Approved Change Requests, Project Management Plan, and Work Performance Data

C. Approved Change Requests, Validated Changes, and PMIS