PMP Exam Set A – Q63

While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this dependency called?

A. Start-to-Finish
B. Start-to-Start
C. Finish-to-Start
D. Finish-to-Finish

D. Finish-to-Finish