PMP Exam Set A – Q70

As part of the Define Scope process, a project manager documented the specific project assumptions associated with the project scope in the project scope statement. While reviewing this document, an experienced project manager pointed out that the project manager should also document:

A. The date on which the assumption becomes invalid.
B. The assigned responsibility for each of the assumptions.
C. The potential impact of the assumptions if they proved to be false.
D. An Assumption Management Plan.

C. The potential impact of the assumptions if they proved to be false.