You have identified a risk that will negatively affect your security project. You and your team have decided to use an older encryption technology because of the high risk associated with the new technology. What type of risk strategy are you using?

A. Mitigation
B. Exploitation
C. Avoidance
D. Transfer

C. Avoidance