PMP Exam Set A – Q78

A project to construct a high-rise building is progressing very well. Stakeholders are proactive in identifying issues related to the quality of the structure, walls and floors. As a project manager, you are conducting meetings to clarify or resolve their issues. Although, you are committed to manage stakeholders concerns, you learned that some critical issues need to be deferred to the next phase of the project for resolution. What should you do in this situation?

A. You must not defer any stakeholder issues but look for alternate methods
B. You must escalate these issues to the sponsor for his advice
C. You must work with stakeholders to defer those issues
D. You must request the stakeholders to retract their issues

C. You must work with stakeholders to defer those issues