PMP Exam Set A – Q87

For any complex project, once the project stakeholders are identified, the next step is to classify these stakeholders based on their current and desired engagement levels. What is the benefit of classifying the project stakeholders?

A. To help identify the project scope
B. To help populate the stakeholder register
C. To help define an approach strategy
D. It is a mandatory step in stakeholder analysis

C. To help define an approach strategy