PMP Exam Set A – Q98

Sally has recently finalized her project management plan and has also got it approved. She is managing a complex manufacturing process improvement project. The project stakeholders’ continuous support and commitment is an absolute must for the success of the project. Which of the following are the most crucial stakeholder management processes at this stage?

A. Plan Stakeholder Management & Manage Stakeholder Engagement
B. Identify Stakeholders & Plan Stakeholder Management
C. Manage Stakeholder Engagement & Control Stakeholder Engagement
D. Plan Stakeholder Management & Control Stakeholder Engagement

C. Manage Stakeholder Engagement & Control Stakeholder Engagement