PMP Exam Set B – Q100

You are an inexperienced project manager who has been appointed to manage a project in a matrix organization. Because of this you can expect the communication in this project to be:

A. Open and Accurate
B. Easy to Automate
C. Simple
D. Complex

D. Complex