PMP Exam Set B – Q15

Jane is a project manager managing a global project. She has stakeholders located in various parts of the globe. Due to the nature of the project, she also has large volumes of information that needs to be shared with the recipients. What type of communication method should she prefer for this purpose?

A. Pull communication
B. Push communication
C. Request based communication
D. Interactive communication

A. Pull communication