PMP Exam Set B – Q35

A project manager was involved in preparation of the project charter for an external project. One of the inputs to the project charter was a statement of work (SOW). The SOW may have been received from the customer as part of all of the following except:

A. As part of a request for information
B. As part of the business case
C. As part of a request for proposal
D. As part of a contract

B. As part of the business case