PMP Exam Set B – Q37 ( PMBOK 6th edition )

John is managing a simple construction project. For this project, the stakeholder register exists, but the stakeholder engagement plan was not developed during the planning phase of the project. During the project execution, a big number of change requests came in and got approved. John now believes that a formal stakeholder engagement plan should be in place in order to guarantee the project’s success. What must John do?

A. Continue with the project and delegate the plan development to one of the project team members.
B. Terminate the project and start the project from scratch.
C. Go ahead and develop the project’s stakeholder engagement plan.
D. Hold the project work till the management prepares the new stakeholder engagement plan.

C. Go ahead and develop the project’s stakeholder engagement plan.