PMP Exam Set B – Q43

Andrew is managing a construction project. He is using his communication, interpersonal and management skills to keep the key project stakeholders engaged with the project. Which of the following activities is not related to the Manage Stakeholder Engagement process?

A. Addressing and resolving issues
B. Adjusting the stakeholder management strategy
C. Confirming the stakeholders’ continued commitment
D. Negotiating and communicating with the stakeholders

B. Adjusting the stakeholder management strategy