PMP Exam Set B – Q55

You are the Project Manager for GeoThermal Systems. Which of the following must be done FIRST before proceeding with a new project?

A. Create the Project Scope Statement
B. Stakeholder analysis
C. Product analysis
D. Obtain Project Charter approval

D. Obtain Project Charter approval