PMP Exam Set B – Q62

Emily is a project manager managing a town-development project. Emily has set up a series of interviews with various stakeholders to gather some experiential and historical information on risks. Which phase is this likely to happen in?

A. Perform Qualitative Risk Analysis
B. Plan Risk Responses
C. Understand Risks
D. Perform Quantitative Risk Analysis

A. Perform Qualitative Risk Analysis