PMP Exam Set B – Q83

During the execution of a project, a large number of defects were discovered. The project manager ensured that the issues, defect resolution and action item results were logged into a defects database. What would the defect database be considered a part of?

A. Expert Judgment
B. Deliverables
C. Change Requests
D. Organizational Process Assets

D. Organizational Process Assets