PMP Exam Set B – Q91 ( PMBOK 6th edition )

Emily is about to review her project stakeholder engagement plan to make some necessary adjustments. She has got her project management plan, the recent issue log and the work performance data. Which of the following inputs is still missing for this process?

A. Project charter
B. Stakeholder engagement plan
C. Project documents
D. Communication management plan

C. Project documents