You are in the execution stage of your project and you have been informed that “corporate” will be sending in a team of consultants to review whether your project activities comply with company’s and PMI’s policies, standards and procedures. This is an example of?

A. Quality Audit
B. Organizational Process Assets
C. Process Analysis
D. Recommended Corrective Actions

A. Quality Audit