PMP Exam Set C – Q27 ( PMBOK 6th edition )

Which of the following activities fall under the planning process group but not under the Project Schedule Management?

A. Estimating the type of materials and equipment needed to perform project activities
B. Developing the Schedule Management Plan
C. Identification of various activities to produce the project deliverables
D. Developing a detailed description of the project and product being developed

D. Developing a detailed description of the project and product being developed