PMP Exam Set C – Q30 ( PMBOK 6th edition )

As part of the Control Procurements process, the project manager prepared a complete set of indexed contract documentation, including the closed contract, to include with the final project files. This is called a:

A. Procurement file
B. Documentation file
C. Closure report
D. Closure file

A. Procurement file