PMP Exam Set C – Q37

Emily has recently taken over a project as the project manager. The project is early in the executing phase. Although, the project scope statement was signed off by all key stakeholders, Emily finds out that some of the key stakeholders do not fully understand the project scope. Stakeholders’ continuous support is very critical for the success of the project. What must Emily do?

A. Email the copy of the scope management plan to the key project stakeholders.
B. Don’t do anything as the scope statement has already been signed by all the key project stakeholders.
C. Email the copy of the scope statement to the key project stakeholders.
D. Conduct one-to-one meeting sessions with these key stakeholders to ensure that they understand the project scope.

D. Conduct one-to-one meeting sessions with these key stakeholders to ensure that they understand the project scope.