PMP Exam Set C – Q41 ( PMBOK 6th edition )

In an underground highway construction project, the project stakeholders have suggested many changes to the project scope. As you have already defined the cost baseline in your project, you would like to revisit the baseline to see how these changes impact the overall cost of the project. So, you have started an impact analysis to determine the impact, and inform the concerned stakeholders of all approved changes and the corresponding costs. You must use the following to carry out such process:

A. Control Scope
B. Monitor Risks
C. Control Costs
D. Monitor Communications

C. Control Costs