PMP Exam Set C – Q45

A Work Breakdown Structure (WBS) dictionary supports the WBS and is a companion document to the WBS. Which of the following is not included in the WBS dictionary?

A. List of schedule milestones
B. Resource assigned
C. Agreement Information
D. Code of Account Identifier

B. Resource assigned