PMP Exam Set C – Q46

In a Finish to Start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity 5 days before its predecessor is complete. This is accomplished by providing 5 days of:

A. Lag
B. Load
C. Fast-tracking
D. Lead

D. Lead