PMP Exam Set C – Q6

Emily is the project manager of a project that has a timeline of 18 months. Emily has planned for daily status reports to be sent out to all stakeholders. After receiving two such reports, the project sponsor informs Emily that she would only like to have fortnightly reports. Emily had done an analysis of communications requirements and considered various attributes for the communications management plan. What aspect has she missed out, which resulted in a daily status report being sent out instead of fortnightly status reports?

A. She has not considered the frequency of information distribution.
B. She has not considered the purpose for distribution of information.
C. She has not considered the timeline of the project.
D. She has not considered the content of the information to be distributed.

A. She has not considered the frequency of information distribution.