PMP Exam Set C – Q61

Which of the following statements most accurately describes a project scenario?

A. Changes in project scope during the initial phases of the project are very expensive.
B. The influence of the stakeholders is the same all through the project.
C. Staffing peaks up during the execution phase of a project.
D. The next phase of a project should never start until the deliverables for the previous phase have been completely reviewed and approved.

C. Staffing peaks up during the execution phase of a project.