PMP Exam Set C – Q74

Midway through the Collect Requirements process, a project manager finds that there are lots of unresolved issues. Which of the following is usually the best way to discover and resolve issues?

A. Interviewing
B. Use of a stakeholder register
C. Questionnaires
D. Facilitated workshops

D. Facilitated workshops