PMP Exam Set C – Q76

A Resource Breakdown Structure (RBS) would be used to breakdown the project by type of resources. The RBS is an example of a:

A. Linear chart
B. Matrix chart
C. Flow chart
D. Hierarchical chart

D. Hierarchical chart