PMP Exam Set C – Q80

The Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create required deliverables. The ‘Create WBS’ is a process under which Knowledge Area?

A. Project Schedule Management
B. Project Integration Management.
C. Project Scope Management
D. Project Cost Management

C. Project Scope Management