PMP Exam Set D – Q10 ( PMBOK 6th edition )

John is the project manager of a large highway expansion project. He has a number of stakeholders with competing priorities and agendas, and often has to resolve conflicts between stakeholders. Which knowledge area manages communications with the project stakeholders?

A. Project Quality Management
B. Project Stakeholder Management
C. Project Communications Management
D. Project Resource Management

C. Project Communications Management