PMP Exam Set D – Q11

You are a non-technical project manager. Two highly skilled and knowledgeable resources on your project are in conflict over the best technical solution to meet a project requirement. It is not impacting the project schedule, however. Who is initially responsible for the conflict resolution?

A. The project sponsor is initially responsible for the conflict resolution.
B. The project manager is initially responsible for the conflict resolution.
C. Both team members are initially responsible for the conflict resolution.
D. Either of team members is responsible for the conflict resolution.

C. Both team members are initially responsible for the conflict resolution.