PMP Exam Set D – Q26

In which of the following situations would it be better to avoid using Analogous Estimating?

A. When the project team members have the needed expertise
B. When an accurate estimate is required
C. When a low value estimate is required
D. When the previous activities are similar in fact and not just appearance

B. When an accurate estimate is required