PMP Exam Set D – Q34

The Quality Policy is the intended direction of a performing organization with regard to quality. As a project manager in a performing organization, you find that the organization lacks a formal quality policy. What should be done in such a case?

A. The project management team need not develop a quality policy since the performing organization does not have one.
B. The project management team needs to obtain the quality policy from the customer.
C. A quality policy is a ‘nice-to-have’ and is not required for every project.
D. The project management team will need to develop a quality policy for the project.

D. The project management team will need to develop a quality policy for the project.