PMP Exam Set D – Q36

The project you are working on has received an invoice from a vendor for USD $17,500. However, your team believes the correct total due is $15,300. When you notify the vendor of this, the vendor still insists on US$ 17,500. What is the best course of action now?

A. Pay $15,300.
B. Negotiate with the vendor.
C. File a lawsuit.
D. Pay $17,500

B. Negotiate with the vendor.