Which of the following scenarios is likely to occur in a project?

A. Cost and staffing levels are low at the start of the project.
B. Stakeholders’ influence on the project is lowest at the start of the project.
C. Risk and uncertainty are lowest at the start of the project.
D. Cost of changes are the highest at the start of the project.

A. Cost and staffing levels are low at the start of the project.