PMP Exam Set D – Q52

A project manager is spending majority of the project funding in the current phase of the project. Not only she is spending her money but also managing various resources in the project. What is the stakeholder influence on the project now compared to earlier phases?

A. Cannot be determined
B. More
C. Less
D. Same

C. Less