PMP Exam Set D – Q89

Which of the following is not accurate about the initial phase of a project?

A. The highest uncertainty is at this stage of the project
B. The cost associated at the beginning of the project is highest
C. Stakeholders have maximum influence during this phase
D. Staffing levels are the highest at this stage

B. The cost associated at the beginning of the project is highest