PMP Exam Set E – Q17

John is managing a computer network deployment project at a university campus. John wants to involve the key project stakeholders in the scheduling of the major work packages. He sends out a meeting invitation to all key stakeholders for this brainstorming session. Which of the following types of communication methods has John selected for the brainstorming?

A. Push communication
B. Interactive communication
C. Pull communication
D. One-sided communication

B. Interactive communication