You have just been assigned a project with an unrealistic deadline. What do you do?

A. Do the best you can to deliver the project on time.
B. Ask for more resources
C. Insist that the deadlines for the project be changed.
D. Ask for a larger budget.

C. Insist that the deadlines for the project be changed.