PMP Exam Set E – Q39

Jonathan has recently been hired in a company as a business improvement manager. Jonathan has been asked to reorganize the company’s meetings and reporting structure. Jonathan is currently identifying all key project stakeholders. Which of the following enterprise environmental factors is least likely to be used as an input to this process?

A. Organizational culture and structure
B. Existing human resources
C. Project management information system.
D. Industry standards

C. Project management information system.