Peter is managing a website development project. He has recently received a feedback from one of the key project stakeholders. The feedback is overall positive but it contains some recommendations. After analyzing the recommendations, Peter accepts them, gets them approved and incorporates them into the project management plan. What needs to be done with this feedback now?

A. Discard it as it is no longer required
B. Publish it on the corporate intranet
C. Add it to the organizational process assets
D. Send it back to the stakeholder

C. Add it to the organizational process assets