You are in the midst of a major code roll out for a new software module. However, it has come to your attention that the resources promised for the roll out are not going to be available. As the Project Manager, what is the BEST thing to do?

A. Explain the impact of the lost resources to the stakeholders
B. Replan the project without the resources
C. Have the current staff work extra hours
D. Fast Track the schedule

A. Explain the impact of the lost resources to the stakeholders