PMP Exam Set E – Q91

The development of requirements in the Collect Requirements process begins with an analysis of the information contained in the _______________ and _______________.

A. Project charter, Stakeholder register
B. Scope baseline, Requirements traceability matrix
C. Scope baseline, Stakeholder register
D. Project charter, Project scope statement