PMP Exam Set F – Q1 ( PMBOK 6th edition )

Jane has been assigned to establish a PMO in her organization. Jane believes that this project cannot be successful unless all of the key project stakeholders support the project. She also believes that she needs to pay special attention on stakeholder management to ensure success of this project. As the first step, she needs to develop her stakeholder register. Which of the following processes must be started by Jane to produce the project stakeholder register?

A. Plan Stakeholder Engagement
B. Monitor Stakeholder Engagement
C. Identify Stakeholders
D. Manage Stakeholder Engagement

C. Identify Stakeholders