PMP Exam Set F – Q22

A RAM diagram shows the relationship between ____________ and ____________ in a tabular format.

A. Cause and effect
B. Risks and mitigation plans
C. Deliverables and costs
D. Work packages and project team members

D. Work packages and project team members