PMP Exam Set F – Q31

During the execution of a project, a need is felt to make major changes to the project stakeholder management plan. What must the project manager do first?

A. Ask the project sponsor for an expert opinion.
B. Directly make the required changes.
C. Issue a change request.
D. Move the project back to planning phase.

C. Issue a change request.