You are a project manager for KTmart and are currently engaged in a highly visible project. The company is about to implement an independent review to ensure that the project work is continuing to comply with the project’s policies, processes, and procedures. During which process would this review occur?

A. Close Project or Phase
B. Control Quality
C. Monitor Risks
D. Manage Quality

D. Manage Quality