PMP Exam Set F – Q65

A project manager is estimating project costs and needs to decide whether the estimates will include only direct costs, or whether the estimates will also include indirect costs. In which of the following phases does this decision need to take place?

A. Define Scope
B. Estimate Costs
C. Plan Expenses
D. Determine Budget

B. Estimate Costs