You have been managing a construction project in a developing country and are closing down the project. The tools and equipment that was used on the project has to be returned to your company’s European headquarters. A non-governmental organization that builds and repairs medical facilities in this country has come to you to request that this equipment be donated to them. What should you do?

A. Donate all tools and equipment.
B. Refuse the request.
C. Donate only the tools and equipment whose value is below your purchase approval limit.
D. Notify the appropriate management.

D. Notify the appropriate management.